< {{#switch:Previous Page | Previous Section = Previous Section | Next Section = Next Section | Previous Page = Previous Page | Next Page = Next Page | }} | {{#switch:Next Page | Previous Section = Previous Section | Next Section = Next Section | Previous Page = Previous Page | Next Page = Next Page | }} > |
DAYS
Returns the number of days between two dates
Syntax:
DAYS(enddate; startdate)
- startdate and enddate may be dates as numbers or text (which is converted to number form).
- DAYS returns enddate - startdate. The result may be negative.
Example:
DAYS("2008-03-03"; "2008-03-01")
- returns 2, the number of days between 1March08 and 3March08.
DAYS(A1; A2)
- where cell A1 contains the date 2008-06-09 and A2 contains 2008-06-02 returns 7.
Issues:
- Note that DAYS does not count the first day of the period, but NETWORKDAYS does.
- DAYS is not portable to Excel.
- DAYS really does return enddate - startdate; thus if either date has a time component (for example "2008-01-03T15:15"), the number of days returned may not be integer. To ensure an integer result, consider INT(DAYS()).