Localization AOO/workPlan

From Apache OpenOffice Wiki
Jump to: navigation, search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Documentation note.png This page is about a proposal, codename genLang, not implemented yet.

The following is a milestone plan for transition from the current l10n to the new l10n.

The plan is updated whenever something major has happened, and only the missing parts are described.

There are 2 separate project, which will be executed in parallel:

Information project

This project is the interface to offline translators, NLC and people interested in l10n.

The milestones are as follows

  • Update all of wiki localization/l10n
  • Update country specific pages and contact NLC to get things running

Due to what seems to a conflict of interest, this part has been postponed

Development project

This project is mainly developer and integrator oriented.

The milestones are as follows:

  • change l10n tools to one tool (genLang) that generates module specific files (instead of a file pr source) and not sdf file
  • build "extraction" in genLang tool
  • update local git branch, with svn trunk (requires committer)
  • build "merge" in genLang tool
  • update local git branch, with svn trunk (requires committer)
  • QA test of "extraction" process
  • update procedures for getting text to pootle
  • build "generate" in genLang tool
  • update local git branch, with svn trunk (requires committer)
  • build "insert" in genLang tool
  • update local git branch, with svn trunk (requires committer)
  • QA test of flow to/from sources
  • change build/make to include new target, I need someone to ping-pong with about the best way forward

The second phase awaits the outcome of a discussion with pootle people (can SVN be used, etc), but assuming yes:

  • Update Pootle server to work on SVN, here I need help since I have no access at all
  • Update Pootle server with missing funnctionality
  • QA whole process, help would be appreciated (4 eyes are better than 2).
  • update documentation.

it can be seen, that I need a lot of communication with a committer just for the pure work, I would anyhow appreciate input/comments from time to time.

The total calendar time needed is about 2 months, if the committer and I have a very close working order.