Based on the current source, we plan to finish the buildhelp development within Four months.
- m1.3weeks:Source downloading ( including designating websites and progress bar etc. )
the Spring Holiday:2weeks
- m2.3weeks:Detection of the building requriments( list the directories of the installed tools )
- m3.4weeks:.Download and installation of the lacked tools and autobuild
- m4.4weeks.Interface optimization and bugfix
Your suggestions will be appreciated.