Usually we use a combined UI and Feature freeze at the same date. At this date all UI changes and all new Features need to beintegrated into the code base. Last translation will be handed over to translation teams. All Features must have been completed to ensure that there is enough time to review the new feature before the next release and incorporate feedback. For OpenOffice.org this is usually 9 weeks before release.
 
Usually we use a combined UI and Feature freeze at the same date. At this date all UI changes and all new Features need to beintegrated into the code base. Last translation will be handed over to translation teams. All Features must have been completed to ensure that there is enough time to review the new feature before the next release and incorporate feedback. For OpenOffice.org this is usually 9 weeks before release.
 
== nomination deadline ==
 
 
qa approval or nominations should be done until 11.59 pm UTC of that days, so that integration of these child workspaces can be performed the next day
 

Revision as of 15:37, 1 September 2009

UI Freeze

At this point all UI changes need to beintegrated into the code base. Last strings for translation will be handed over to localization teams. For OpenOffice.org this is usually 9 weeks before release.

Feature Freeze

At this point all new Features need to be integrated into the code base. All Features must have been completed to ensure that there is enough time to review the new feature before the next release and incorporate feedback. For OpenOffice.org this is usually 9 weeks before release.

UI/Feature Freeze

Usually we use a combined UI and Feature freeze at the same date. At this date all UI changes and all new Features need to beintegrated into the code base. Last translation will be handed over to translation teams. All Features must have been completed to ensure that there is enough time to review the new feature before the next release and incorporate feedback. For OpenOffice.org this is usually 9 weeks before release.