Based on the current source, we plan to finish the buildhelp development within Four months.

  • m1.3weeks:Source downloading ( including designating websites and progress bar etc. )

the Spring Holiday:2weeks

  • m2.3weeks:Detection of the building requriments( list the directories of the installed tools )
  • m3.4weeks:.Download and installation of the lacked tools and autobuild
  • m4.4weeks.Interface optimization and bugfix

Your suggestions will be appreciated.